Project objectives

The main goal of the project is to design and implement the blockchain operation dashboard and API server, which helps users to operate and manage the blockchain network nodes without the blockchain background knowledge and can connect blockchain networks among multiple organizations.

Milestones

A tentative schedule below. 

TimeTasks/PlanDeliverables
Week 1 to Week 6
  • Understand Cello User-Dashboard API Design and Docker Agent API. 
  • Look into the source code API-Engine Part. 
  • Set up the development environment and tools.
  • Project Plan 
  • 1st Quarter Evaluation   
Week 7 to Week 12
  • Connect agent and API engine.
  • Help writing related documentation.
  • Complete connection between agent and API-engine.  
  • Midterm Quater Evaluation.  
Week 13 to Week 18
  • Implement channel part of API engine.
  • Help writing related documentation.
  • Complete channel part of API engine 
  • 3rd Quarter Evaluation   
Week 19 to Week 24
  • Wrap up documentation.
  • Demo what I did to the cello community. 
  • Final Project report
  • Code for testings.  
  • Final Report.  
  • Final Deni.  
  •  

Methodology and Documentation

  • Communication and updates
    • participate in weekly zoom meetings.
    • summarize weekly contributes and updates to the WeChat group.
    • emails 
  • Quarter basis review according to Hyperledger Internship Programme schedule.