Date

Recording

Cactus-Maintainers-Call-2020-09-28.mp4

Attendees

Discussion items

TimeItemWhoNotes
25 min

New timeline

Peter, Shingo, Clive

Peter suggested a new timeline of Cactus. Its replies are as the following:

  • Automation program is too challenging in this timeline.  It should be postponed after version 1.
  • Ledger Plugin is much more important then the development of Ledger Plugin should be prioritized.

Peter agreed on the above replies. 

30 minOutstanding PRsTakuma, Shingo, Peter

PR #298 - Sequence diagram

  • Takuma and Shingo proposed a sequence diagram on Cactus architecutre
  • Peter will develop plugins generating logging system of standard errors using npm packages

Some sort of agree is achieved and the result will be reflected on the updated timeline.

Action items

  • No labels