Overview


Tasks and Deliverables


ScheduleTaskDeliverable

Week 1 - Week 2

Jun 1 - Jun 13

  • Install Ubuntu 20.04 LTS and set up environment.
  • Build Cactus.
  • Build Iroha.
  • Study existing source code.
  • Project Plan.

Week 3 - Week 7

Jun 14 - July 18

Jun 18: 1st Quarter Evaluation

July 9: 2nd Quarter Evaluation

  • Implement Iroha and Cactus integration.
  • Write tests for Iroha and Cactus integration.
  • Write comments.


  • Code for Iroha and Cactus integration.
  • Technical documentation for code.

Week 7 - Week 10

July 19 - Aug 1st

July 30: 3rd Quarter Evaluation

  • (2 and more) Examples of Iroha and Cactus integration.
  • Examples of Iroha and Fabric integration.
  • Write tests for Iroha and Cactus integration.
  • Write tests for Iroha and Fabric integration.
  • Write comments.
  • Examples of Iroha and Cactus integration.
  • Examples of Iroha and Fabric integration.
  • Code for unit tests and integration tests.

Week 11

Aug 2 - Aug 5

Aug 20-31: Final Evaluation

  • Wrap up comments.
  • Final report of the project.
  • Well-documented techinical comments.
  • Final report of the project.
  • Final presentation.

Processes

  • Quarter basis review according to Summer Full-Time Mentee Schedule
  • Internal communication and updates:
    • RocketChat/Telegram/Channels is used for communications and updates
    • Weekly meetings via Microsoft Teams are scheduled to check-in with mentors.