WeekTask/PlanStatus
May 24 - May 28Initial Project Plan.Done
May 31 - June 11Introduction to project.  Download the code from the branch and get familiar with the code.  Learn the key functionalities of Hyperledger Fabric.  Structure the already existing tests in unit, integration, and functional. Bring all the existing tests to work.
June 14 - June 25Integrate the existing tests into GitHub Actions Pipeline, which gets triggered by every PR and Push to the master branch.  
June 28 - July 2Wrap up all tasks prior to Eval 1
July 5 - July 9

Review all existing tests, their organization, and integration into github actions pipeline.

Eval 1



July 12 - July 23 Extend the overall test coverage. Develop some key end-to-end tests
July 26 - August 6

August 9 - August 13

August 16 - August 27


Eval 2



August 30 - Sept 3

Sept 6 - Sept 17

Sept 20 - 24



Sept 27 - Oct 1


Eval 3



Oct 4 - Oct 15



Oct 18 - Oct 29



Nov 1 - Nov 5

Nov 8 - Nov 12

Eval 4

Final evaluation and presentation of project 



Tasks

Github issues macro
querylabels=mentorship-testing
repoblockchain-carbon-accounting
userhyperledger-labs
token4


Explanation

Explanation of the project goes here.

...

Methodology followed is here.



Github issues macro
query labels=mentorship-testing
repoblockchain-carbon-accounting
userhyperledger-labs
token4