Communication channel:  Discord+ Github

Project repo:    https://github.com/hyperledger-tooling/start-here-hyperledger/getting-started

Deployed Link: https://getting-started-flame.vercel.app/

Figma Design:

Widget Connector
urlhttps://www.figma.com/file/Z1DSassHZpRfuSoKeOy2cr/Hyperledger-Website?t=G8lGkLKm8KxzrVeM-0

Deliverables

  •   Improve User Experience - From Getting Started With Hyperledger To Continuous Engagement
  •  Dashboard and the landing page for driving the user engagement.
  •  Ability to search events and happenings within the Hyperledger community.
  •  Find out all things project information from the user engagement portal.

...

Final Project Presentation:

  • Widget Connector
    urlhttps://docs.google.com/presentation/d/1_ERdp1ooQzO3kwgEqo5SDkZfWqnEtPva/edit?usp=sharing&ouid=104074652179550938833&rtpof=true&sd=true
    TBD

Milestones

Eval 1:

  •  TBD

Eval 2:

  •  TBD

Eval 3:

  •  TBD

Eval 4:

...

Dates

Tasks/Plan

Status

Dates

Tasks/Plan

Status

June 1 - June 14Mentee intro with the mentor. Completed
June 15 - June 28Create project planCompleted

June 29 - July 12

Doing Research on users and Understanding the user problemsCompleted
July 13 - July 26Creating the 1st Iteration of UICompleted
July 27 - Aug 9Getting it approved by the mentorsCompleted
Aug 10 - Aug 23Creating 2nd Iteration of the DesignCompleted
Aug 24 - Sept 6Start creating the frontendCompleted
Sept 7 - Sept 20Finishing off the frontendIn Progress
Sept 21 - Oct 4Creating the Backend.In Progress
Oct 5 - Oct 18Connecting the Backend to frontendIn Progress
Oct 19 - Nov 1Deploying the project In Progress
Nov 2 - Nov 12Final Presentation of the projectIn Progress

Methodology

TBD