Abstract


Hyperledger India Chapter started with the https://start-here.hyperledger.org to help new developers look for contribution opportunities. The tool provides an option to see through a list of all "Good First Issues", "Open PRs" and "Releases".

The requirement, in this proposal, is to extend or improve the website to include - role-based navigation (eg. Developer, Business User, Contributor, etc) to information. The process will involve adding easy to access links or information for project documentation, community contribution guidelines, guiding (new & experienced) users towards how to start & what tasks require contribution, informing the latest happenings within the community (i.e. figuring out available events and meetups), and Calendar(s). The cherry on top of it would be to have navigations defined for different users and search capability.

The task would start with the survey on what somebody looks for within the community, understand what troubles them. The project is aimed at providing an improved user experience.

Mentors

Name

Time zone

Discord ID

Email ID

Arun S MIST arsulegai#7968arun.s.m.cse@gmail.com
Vikram SharmaIST Sharmawiki#1283 vikram13sharma@gmail.com
Kamlesh NagwareISTknagware#6976kamlesh.nagware@gmail.com

Mentee

Name

Time zone

Discord ID

Email ID

Niku SinghISTNiku#1433soapmactavishmw4@gmail.com
nikusingh319@gmail.com 

Communication channel:  Discord+ Github

Project repo:  https://github.com/hyperledger-tooling/getting-started

Deployed Link: https://getting-started-flame.vercel.app/

Figma Design:

Deliverables

  •  Improve User Experience - From Getting Started With Hyperledger To Continuous Engagement
  • Dashboard and the landing page for driving the user engagement.
  • Ability to search events and happenings within the Hyperledger community.
  • Find out all things project information from the user engagement portal.

Merged PR's

  • TBD
  • TBD
  • TBD

Final Project Presentation:

Milestones

Eval 1:

  • TBD

Eval 2:

  • TBD

Eval 3:

  • TBD

Eval 4:

  • TBD

Timeline

Dates

Tasks/Plan

Status

Dates

Tasks/Plan

Status

June 1 - June 14Mentee intro with the mentor. Completed
June 15 - June 28Create project planCompleted

June 29 - July 12

Doing Research on users and Understanding the user problemsCompleted
July 13 - July 26Creating the 1st Iteration of UICompleted
July 27 - Aug 9Getting it approved by the mentorsCompleted
Aug 10 - Aug 23Creating 2nd Iteration of the DesignCompleted
Aug 24 - Sept 6Start creating the frontendCompleted
Sept 7 - Sept 20Finishing off the frontendIn Progress
Sept 21 - Oct 4Creating the Backend.In Progress
Oct 5 - Oct 18Connecting the Backend to frontendIn Progress
Oct 19 - Nov 1Deploying the project In Progress
Nov 2 - Nov 12Final Presentation of the projectIn Progress

Methodology

TBD