The tentative timeline is as follows:

Week

Deliverables

Week 1 - Week 6 


  •  Understanding chaincode lifecycle management and features that have not yet been implemented for compatibility with Fabric 2.x.
  •  Revise channel function and compability in sdk.
  •  Review the documentation for the existing code and make appropriate changes.

Week 7 - Week 12


  •  Implement APIs for chaincode lifecycle management
  •  Implement the remaining features for the release of Fabric Python SDK 2.0 LTS.
Week 13 - Week 18
  •  Add chaincode examples with new APIs
  •  Update documentations and unittest cases
Week 19 - Week 24
  •  Complete implementation of the possible features for compatibility with 2.0.
  •  Document the newly implemented features.These are certain deviations from the original project plan


Newly opened issues will also be resolved during the course of the project.

...

  • Review and evaluation will be done on a quarterly basis as mentioned in the Program Timeline.
  • All communications between the mentee and mentors will be done through rocket chat and bi-weekly meetings over zoom. 

Result

Updated Fabric Python SDK documentations: https://fabric-sdk-py.readthedocs.io/en/latest/

Relevant Repository: https://github.com/hyperledger/fabric-sdk-py

Final Report:

View file