Dates

Tasks/Plan

Status

Dates

Tasks/Plan

Status

June 1 - June 14Mentee intro with the mentor. Completed
June 15 - June 28Create project planCompleted

June 29 - July 12

Doing Research on users and Understanding the user problemsCompleted
July 13 - July 26Creating the 1st Iteration of UICompleted
July 27 - Aug 9Getting it approved by the mentorsCompleted
Aug 10 - Aug 23Creating 2nd Iteration of the DesignCompleted
Aug 24 - Sept 6Start creating the frontendCompleted
Sept 7 - Sept 20Finishing off the frontendIn Progress
Sept 21 - Oct 4Creating the Backend.In Progress
Oct 5 - Oct 18Connecting the Backend to frontendIn Progress
Oct 19 - Nov 1Deploying the project In Progress
Nov 2 - Nov 12Final Presentation of the projectIn Progress

Methodology

TBD