Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Dates

Tasks/Plan

Expectations Evaluation

Status

June 1 - June 14

Mentee intro with the mentors.

Introduction to the concepts of HLF Connector Lab project

Setup and run a local instance of Besu ( https://besu.hyperledger.org/en/stable/Tutorials/Developer-Quickstart/)

Integration Test Setup for Eth Connector  

June 15 - June 28
Quarter Evaluation (June 29th)Quarter Evaluation (June 29th)

June 29 - July 12





July 13 - July 26
MidTerm Evaluation (July 15th)MidTerm Evaluation (July 15th)
July 27 - Aug 9
Quarter Evaluation (July 31st)Quarter Evaluation (July 31st)
Aug 10 - Aug 23
Final Evaluation (Aug 24th)Final Evaluation (Aug 24th)
W0
June 1-4

W1
June 6-12

Mentee onboarding

✔️

W2
June 13-19AIO Chia image creation

✔️

W3
June 20-26

Quarter Evaluation

Finalizing AIO image, releasing it to github container registry

W4
June 27 - July 3Generating code using OpenAPIW5
July 4-10Generating code using OpenAPIW6
July 11-17

Midterm Evaluation

Developing the chia plugin and writing tests

W7
July 18-24Developing the chia plugin and writing tests

W8
July 25-31

Developing the chia plugin and writing testsW9
Aug 1-7

Quarter Evaluation

Developing the chia plugin and writing tests

W10
Aug 8-14Project revisionW11
Aug 15-21Finalizing projectW12
Aug 22-28

Final Evaluation

Finalizing project



Methodology

TBD