Dates

Tasks/Plan

Expectations Evaluation

Status

June 1 - June 14

Mentee intro with the mentors.

Introduction to the concepts of HLF Connector Lab project

Setup and run a local instance of Besu ( https://besu.hyperledger.org/en/stable/Tutorials/Developer-Quickstart/)

Integration Test Setup for Eth Connector  

June 15 - June 28
Quarter Evaluation (June 29th)Quarter Evaluation (June 29th)

June 29 - July 12





July 13 - July 26
MidTerm Evaluation (July 15th)MidTerm Evaluation (July 15th)
July 27 - Aug 9
Quarter Evaluation (July 31st)Quarter Evaluation (July 31st)
Aug 10 - Aug 23
Final Evaluation (Aug 24th)Final Evaluation (Aug 24th)

W0
June 1-4


W1
June 6-12

Mentee onboarding

✔️

W2
June 13-19
AIO Chia image creation

✔️

W3
June 20-26

Quarter Evaluation

Finalizing AIO image, releasing it to github container registry


W4
June 27 - July 3
Generating code using OpenAPI
W5
July 4-10
Generating code using OpenAPI
W6
July 11-17

Midterm Evaluation

Developing the chia plugin and writing tests


W7
July 18-24
Developing the chia plugin and writing tests

W8
July 25-31

Developing the chia plugin and writing tests
W9
Aug 1-7

Quarter Evaluation

Developing the chia plugin and writing tests


W10
Aug 8-14
Project revision
W11
Aug 15-21
Finalizing project
W12
Aug 22-28

Final Evaluation

Finalizing project


Methodology

TBD