Dates | Task/Plan | Status |
---|---|---|
June 1 - June 14 | Mentee intro with the mentor. Introduction to the concepts of BAF. | Done |
June 15 - June 28 | Setup local environment for Development | Done |
June 29 - July 12 | Setup a Besu network with clique consensus manually/locally using Besu documentation. Eval on July 10: Provide reports for first quarter to the program organisers. | Done Eval Completed |
July 13 - July 26 | Setup GKE environment for Development (added because local minikube was not feasible due to memory issues) | Done |
July 27 - Aug 9 | Complete local Besu network with clique consensus. | Done |
August 10 - August 23 | Set-up a small Besu network using local/GKE Kubernetes network using BAF. Eval on August 20: Provide reports for first quarter to the program organisers. | Done Eval Completed |
August 24 - Sept 6 | Document changes needed to implement Clique consensus. | In ProgressDone |
Sept 7 - Sept 20 | Make the changes in Ansible and Helm charts. | PendingIn Progress |
Sept 21 - Oct 4 | Test the scripts and make additional changes in Ansible and Helm charts. Eval on October 1: Provide reports for second quarter to the program organisers. | Pending Eval Pending |
Oct 5 - Oct 18 | Buffer to complete the Besu network deployment using Clique. | Pending |
Oct 19 - Nov 1 | Update the documentation. | Pending |
Nov 2 - Nov 12 | Prepare final presentation. Final Eval on November 12: Provide reports for completion. | Pending Eval Pending |
...