WeekTask/PlanStatus
Sep 1 - Sep 5Initial Project Plan.
Sep 6 - Sep 20Introduction to project.  Download the code from the branch and get familiar with the code.  Learn the key functionalities of Hyperledger Fabric.  Structure the already existing tests in unit, integration, and functional. Bring all   Get the existing tests to work and check the emissions factors are retrieved for correct year.
Sep 27 - Oct 4Integrate the existing tests into GitHub Actions Pipeline, which gets triggered by every PR and Push to the master branch.  
Oct 4 - Oct 15

Wrap up all tasks prior to Eval 1

Eval 1 on October 15


Oct 18 - Nov 1



Nov 1 - Nov 15

Nov 15 - Nov 29Eval 2 on November 30
Nov 29 - Dec 13

Dec 13 - Dec 27



Dec 27 - Jan 10Eval 3 on January 15
Jan 10 - Jan 24

Jan 24 - Feb 7



Feb 7 - Feb 21





Feb 21 - Feb 28

Final evaluation and presentation of project on February 28


...