DatesTask/PlanStatus
June 1 - June 14Mentee intro with the mentor. Introduction to the concepts of BAF.Done
June 15 - June 28

Setup local environment for Development

Done
June 29 - July 12

Setup a Besu network with clique consensus manually/locally using Besu documentation.

Eval on July 10: Provide reports for first quarter to the program organisers.

Done

Eval Completed

July 13 - July 26

Setup GKE environment for Development (added because local minikube was not feasible due to memory issues)

Done
July 27 - Aug 9

Complete local Besu network with clique consensus.

Done

August 10 - August 23

Set-up a small Besu network using local/GKE Kubernetes network using BAF.

Eval on August 20: Provide reports for first quarter to the program organisers.

In Progress Done 

Eval Completed

August 24 - Sept 6Document changes needed to implement Clique consensus.In Progress
Sept 7 - Sept 20Make the changes in Ansible and Helm charts.Pending
Sept 21 - Oct 4

Test the scripts and make additional changes in Ansible and Helm charts.

Eval on October 1: Provide reports for second quarter to the program organisers.

Pending

Eval Pending

Oct 5 - Oct 18

Buffer to complete the Besu network deployment using Clique.

Pending
Oct 19 - Nov 1

Update the documentation.

Pending
Nov 2 - Nov 12

Prepare final presentation.

Final Eval on November 12: Provide reports for completion.

Pending

Eval Pending

...