Schedule | Task | Deliverable |
---|
Week 1 - Week 3 Jun 1 - Jun 18 Jun 18: 1st Quarter Evaluation | - Install Ubuntu 20.04 LTS and set up environment.
- Build Cactus.
- Build Iroha.
- Understand existing source code.
- Start the Iroha and Cactus integration.
| - Project Plan.
- Skeleton for Iroha and Cactus integration.
|
Week 3 - Week 6 Jun 19 - July 9 July 9: Midterm Quarter Evaluation | - Implement the Iroha and Cactus integration.
- Write tests for the Iroha and Cactus integration.
- Write documentation.
| - Near-complete package for ~50% of the Iroha and Cactus integration package.
- Technical documentation for the package.
|
Week 6 - Week 10 July 10 - July 30 July 30: 3rd Quarter Evaluation | - (2 and more) examples of Iroha and Cactus integration.
- 2 examples of Iroha and Fabric integration.
- Write tests for Iroha and Cactus integration.
- Write tests for Iroha and Fabric integration.
- Write documentation.
| - Completed package for Iroha and Cactus integration.
- 3 examples of Iroha and Cactus integration.
- 2 examples of Iroha and Fabric integration.
|
Week 10 July 31 - Aug 10 Aug 20-31: Final Evaluation | - Wrap up documentation.
- Final report of the project.
- Final presentation of the project
| - Code for unit tests and integration tests. *
- Technical documentation for the entire project.
- Final report.
- Final presentation.
|