Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Mentor and Mentee

MentorMentorMentee

Peter Somogyvari

PDT (UTC-7)

peter.somogyvari@accenture.com

Robin KlemensGrzegorz Baz

CEST (UTC+2)

g.bazior@yodiss.pl

Han Xu

EST (UTC-5)

hongkexuhan@gmail.com

...

ScheduleTaskDeliverable

Week 1 - Week 3

Jun 1 - Jun 18

Jun 18: 1st Quarter Evaluation

  •  Install Ubuntu 20.04 LTS and set up environment.
  •  Build Cactus.
  •  Build Iroha.
  •  Understand existing source code.
  •  Start the Iroha and Cactus integration.
  •  Project Plan.
  •  Skeleton for Iroha and Cactus integration.

Week 3 - Week 6

Jun 19 - July 9

July 9: 2nd Quarter Midterm Quarter Evaluation

  •  Implement the Iroha and Cactus integration.
  •  Write tests for the Iroha and Cactus integration.
  •  Write commentsdocumentation.
  •  Near-complete package for Iroha and Cactus integration.
  •  Technical documentation for the package.

Week 6 - Week 10

July 10 - July 30

July 30: 3rd Quarter Evaluation

  •  (2 and more) Examples examples of Iroha and Cactus integration.
  •  Examples 2 examples of Iroha and Fabric integration.
  •  Write tests for Iroha and Cactus integration.
  •  Write tests for Iroha and Fabric integration.
  •  Write commentsdocumentation.
  •  Completed package for Iroha and Cactus integration.
  •  3 examples of Iroha and Cactus integration.
  •  2 examples of Iroha and Fabric integration.

Week 10

July 31 - Aug 10

Aug 20-31: Final Evaluation

  •  Wrap up commentsdocumentation.
  •  Final report of the project.
  •  Final presentation of the project
  •  Code for unit tests and integration tests. *
  •  Technical documentation for the whole entire project.
  •  Final report.
  •  Final presentation.

...

  • Communication and updates:
    • Telegram/ RocketChat/ Public Channels/ Emails/ Microsoft Teams are used as tools.
    • Weekly check-in meetings between the mentors and the mentee.
  • Quarterly review according to Summer Full-Time Mentee Scheduleevaluations on Jun 18/ July 9/ July 30/ Aug 20.