https://github.com/hyperledger/iroha

Project Plan

ScheduleTaskDeliverableExpected deliverable for that period

Week 1 - Week 3

Jun 1 - Jun 20

Jun 18: 1st Quarter Evaluation

  •  Install Ubuntu 20.04 LTS and set up environment.
  •  Build Cactus.
  •  Build Iroha.
  •  Understand existing source code.
  •  Start the Iroha and Cactus integration.
  •  Project Plan.
  •  Skeleton for Iroha and Cactus integration.

Week 4 - Week 76

Jun 21 - July 189

July 9: 2nd Quarter Evaluation

  •  Implement the Iroha and Cactus integration.
  •  Write tests for the Iroha and Cactus integration.
  •  Write comments.
  •  Code for Iroha and Cactus integration.
  •  Technical documentation for code.

Week 8 6 - Week 10

July 19 10 - Aug 8July 30

July 30: 3rd Quarter Evaluation

  •  (2 and more) Examples of Iroha and Cactus integration.
  •  Examples of Iroha and Fabric integration.
  •  Write tests for Iroha and Cactus integration.
  •  Write tests for Iroha and Fabric integration.
  •  Write comments.
  •  Examples of Iroha and Cactus integration.
  •  Examples of Iroha and Fabric integration.
  •  Code for unit tests and integration tests.

Week 1110

Aug 9 July 31 - Aug 15

Aug 20-31: Final Evaluation

  •  Wrap up comments.
  •  Final report of the project.
  •  Final presentation of the project
  •  Code for unit tests and integration tests. *
  •  Technical documentation for the whole project.
  •  Final report.
  •  Final presentation.

* Will try to wrap up all codes-relevant stuff before Aug 5th.

Process

  • Communication and updates:
    • Telegram/ RocketChat/ Public Channels/ Emails/ Microsoft Teams are used as tools.