ScheduleTaskDeliverable

Week 1 - Week 2

Jun 1 - Jun 13

  •  Install Ubuntu 20.04 LTS and set up environment.
  •  Build Cactus.
  •  Build Iroha.
  •  Study Understand existing source code.
  •  Project Plan.

Week 3 - Week 7

Jun 14 - July 18

Jun 18: 1st Quarter Evaluation

July 9: 2nd Quarter Evaluation

  •  Implement Iroha and Cactus integration.
  •  Write tests for Iroha and Cactus integration.
  •  Write comments.
  •  Code for Iroha and Cactus integration.
  •  Technical documentation for code.

Week 7 - Week 10

July 19 - Aug 1st

July 30: 3rd Quarter Evaluation

  •  (2 and more) Examples of Iroha and Cactus integration.
  •  Examples of Iroha and Fabric integration.
  •  Write tests for Iroha and Cactus integration.
  •  Write tests for Iroha and Fabric integration.
  •  Write comments.
  •  Examples of Iroha and Cactus integration.
  •  Examples of Iroha and Fabric integration.
  •  Code for unit tests and integration tests.

Week 11

Aug 2 - Aug 5

Aug 20-31: Final Evaluation

  •  Wrap up comments.
  •  Final report of the project.
  •  Final presentation of the project
  •  Technical documentation for the whole project Well-documented techinical comments.
  •  Final report of the project.
  •  Final presentation.

Processes

...