The main sections of the project are updating the user configuration and the command handling when a signing or verifying operation occur. The actions needed in each section can be listed below and will be evolving as the project evolves.

Below in an illustrative model of the expected outcome:

Image Added

Milestones

  •  Submit project proposal (June 18)
  •  Review previous work (June 25)
  •  RFC with the technical design document sent to git mailing list (July 15)
  •  Receive feedback (August 31)
  •  RFC patchbomb to the mailing list (September 30)
  •  Refine implementation and follow through to landing (November 30)

...