- Basic programming skills
- Basic Linux literacy (Bash)
- Basic understanding of Docker
Project plan
Schedule | Activity | Deliverables | As a Student, I will learn: |
Week 1 - Week 2 June 1 - June 15 |
|
| |
Week 3 - Week 4 June 15 - June 29 |
|
|
|
Week 5 - Week 6 June 29 - July 13 July 10: First Quarterly Evaluation |
|
|
|
Report on the First Quarterly Evaluation | All activities defined for weeks 1-6 were successfully conducted. | All projected deliveries were published. | |
Week 7 - Week 8 July 13 - July 27 |
|
| |
Week 9 - Week 10 July 27 - August 3 |
|
| |
Week 11 - Week 12 August 3 - August 17 |
|
| |
Report on the Second Quarterly Evaluation | All activities up to week 12 were successfully conducted. A minor change in the project plan took place. | The first pre-release of the course is available: https://github.com/hyperledger-labs/university-course/releases/tag/0.1 | |
Week 13 - Week 14 August 17 - August 31 August 21: Second Quarterly Evaluation |
|
| |
Week 15 - Week 16 August 31 - September 14 |
|
| |
Week 17 - Week 18 September 14 - September 28 |
|
| |
Week 19 - Week 20 September 28 - October 12 October 2: Third Quarterly Evaluation |
|
| |
Week 21 - Week 22 October 12 - October 26 |
|
| |
Week 23 - Week 24 October 26 - November 9 |
|
| |
Week 24 November 9 - November 13 November 13: Fourth Quarterly Evaluation |
|
|
Processes
- The project will be publicly available as an Hyperleder Lab (including but not limited to source code, class guides, LATEX files, and presentation files).
- Coordination with related Hyperledger Internship programmes will be hold (Adding Network Fuzzing Capabilities to Hyperledger Umbra and Scaling Experiments with Hyperledger Umbra) so that the outcome of this internship can benefit from up-to-date efforts regarding Umbra.
- Quarter basis review according to the Hyperledger Internship Programme schedule
- Internal communication and updates:
- Rocket Chat/Email for communication
- Weekly meeting for project discussion
...