Week # | Week | Activity | Status |
0 | June 18 -June 22 | First contact with mentor and discussion. | Completed |
1-3 | June 22 - June 29 | Development of the Project Plan and Bi Wallet setup and analysis | Completed |
4-6 | June 29 - July 15 Evaluation 1 | Generate DID scripts and integration with the Bifold app | In-Progress |
7-8 | July 12 - July 25 | Discuss and create architecture | In-ProgressNot Started |
9-10 | July 26 - August 8 Evaluation 2 | Integration with AnoCreds | In-ProgressNot Started |
11-14 | August 9 - September 5 | Resolve issues and feedback given by mentors | In-ProgressNot Started |
15-18 | September 6 - October 3 Evaluation 3 | Design a modular architecture | In-ProgressNot Started |
19-20 | October 4 - October 17 | Start the implementation | In-ProgressNot Started |
21-22 | October 18 - October 31 | Deployment and Go live | In-ProgressNot Started |
23-24 | November 1 - November 14 Evaluation 4 | Complete documentation | In-ProgressNot Started |