This project focuses on bringing the functionalities of the DIDMan Registry Manager to the Bifold wallet. The Bifold wallet will then be able to manage Decentralized Identifier Registries (DID Registries) on GitHub in similar ways. This includes creating new DID Registries for organizations, similar to how organizations can create develop repositories on GitHub. Additionally, users can manage access permissions for members within their organization, allowing granular control over who can access a specific DID Registry. Finally, the Bifold wallet will offer a set of tools to manage DID documents stored within the DID Registry. These tools will allow users to add new DIDs, update existing ones, and revoke access to them.

Mentor and Mentee

Mentors: 

...

  •  

    Generating a DID registry creation script for the Bifold application

  •  Scripts to add access to members of an organization or registry
  •  Scripts to update access control for the DID registry
  •  Integration with Hyperledger AnoCreds specifications

Milestones

Evaluation 1:

  •  Generating a DID registry creation script
  •  Integration with the bifold application

Evaluation 2:

  •  Scripts to add access to members of an organization or registry
  •  Improvise the Bifold app to add members and access from the admin side
  •  Integration with AnoCreds

Evaluation 3:

  •  Develop the complete Architecture
  •  Install required modules like plugins
  •  Test the application

Evaluation 4: 

  •  Complete Application testing and Final review
  •  Write a complete documentation for the project
  •  Go Live

Timeline

Week #

Week

Activity

Status

0

June 18 -June 22

First contact with mentor and discussion.

Completed

1-3

June 22 - June 29

Development of the Project Plan and Bi Wallet setup and analysis

Completed

4-6

June 29 - July 15

Evaluation 1

Generate DID scripts and integration with the Bifold app
Completed
In-Progress

7-8

July 12 - July 25

Discuss and create architecture

Completed
In-Progress

9-10

July 26 - August 8

Evaluation 2

Integration with

Ano

AnoCreds

Completed
In-Progress

11-14

August 9 - September 5

Resolve issues and feedback given by mentors

Completed
In-Progress

15-18

September 6 - October 3

Evaluation 3

Design a modular architecture

Completed
In-Progress

19-20

October 4 - October 17

Start the implementation

Completed
In-Progress

21-22

October 18 - October 31

Discuss on future work and create a skeleton

Deployment and Go live

In-Progress
Completed

23-24

November 1 - November 14

Evaluation 4

Complete documentation

In-Progress