Week #

Week

Activity

Status

0

June 18 -June 22

First contact with mentor and discussion.

Completed

1-3

June 22 - June 29

Development of the Project Plan and Bi Wallet setup and analysis

Completed

4-6

June 29 - July 15

Evaluation 1

Generate DID scripts and integration with the Bifold appIn-Progress

7-8

July 12 - July 25

Discuss and create architecture

In-ProgressNot Started

9-10

July 26 - August 8

Evaluation 2

Integration with AnoCreds

In-ProgressNot Started

11-14

August 9 - September 5

Resolve issues and feedback given by mentors

In-ProgressNot Started

15-18

September 6 - October 3

Evaluation 3

Design a modular architecture

In-ProgressNot Started

19-20

October 4 - October 17

Start the implementation

In-ProgressNot Started

21-22

October 18 - October 31

Deployment and Go live

In-ProgressNot Started

23-24

November 1 - November 14

Evaluation 4

Complete documentation

In-ProgressNot Started