DatesTasks/Plan

Status

Jun 12 - Jun 26Define project scope, onboard mentee, mentor-mentee interaction
  •  
Jun 27 - Jul 10Checking user Experience - From Getting Started With Hyperledger To Continuous Engagement .
  •  

Jul 11 - Jul 24

 Develop dashboard and landing page for user engagement.
  •  
Jul 25 - Aug 7 (Jul 28 eval)
  •   Start Here Webpage Enhancements. Implement event and happening search functionality.
  •  
Aug 8 - Aug 21 Create the user engagement portal. Establish an SEO-friendly framework.
  •  

Aug 22 - Sep 4 (Sept 1 eval)

Enable all users, not just developers, to comment on the future direction of Hyperledger projects, fostering a collaborative environment and gathering valuable insights.
  •  
Sep 5 - Sep 18
  •  Ensure that all development work and design layouts for the Start Here webpage are compatible with the new website design managed by Ben at Hyperledger.
  •  
Sep 19 - Oct 2

Include additional items like SIGs and Working Groups into the Start Here navigation. Address feedback and make adjustments.

  •  
Oct 3 - Oct 16 (Oct 13 eval)
  •   Finalize all deliverables and conduct a comprehensive review.
  •  
Oct 16 - Oct 30

Create a presentation summarizing the onboarding enhancements and their impact on the user experience.

  •  
Oct 31 - Nov 6
  •   Documentation and final project wrap-up.
  •  
Nov 7 - Nov 30 (Nov 30 eval)
  •   Final evaluation, completion of remaining tasks
  •  


Methodology

The Hyperledger Onboarding Enhancement project will follow an iterative and collaborative methodology to ensure the successful implementation of the proposed enhancements. The methodology will consist of the following key steps:

...