Mentee

Akanksha Rani, Email: akankshar8800@gmail.com , Discord: unishe

Deliverables

...

Bonus Deliverables

  •  TBD

Milestones

Eval Evaluation 1:

Eval 2:

Assess project requirements, finalize mentor/mentee recruitment, and define scope.

Review progress on dashboard and landing page development, event and happening search implementation, and SEO-friendly framework.

Evaluation 2:

 Evaluate the completion of the user engagement portal, design alignment, and overall project progress.\

 Final evaluation, addressing feedback and issues, documentation, and project closure.

Timeline

DatesTasks/Plan

Status

Jun 12 - Jun 26Define project scope, onboard mentee, mentor-mentee interaction
Jun 27 - Jul 10Develop dashboard and landing page for user engagement.

Jul 11 - Jul 24

Implement event and happening search functionality.
Jul 25 - Aug 7 (Jul 28 eval)
  •    Create the user engagement portal.

Aug 8 - Aug 21Establish an SEO-friendly framework.

Aug 22 - Sep 4 (Sept 1 eval)

Align designs with Ben's website design.
Sep 5 - Sep 18
  •  Fine-tuning and testing of the mentor/mentee program.

Sep 19 - Oct 2Address feedback and make adjustments.
Oct 3 - Oct 16 (Oct 13 eval)
  •    Finalize all deliverables and conduct a comprehensive review.

Oct 16 - Oct 30

Address any feedback or issues from the evaluation


Oct 31 - Nov 6
  •    Documentation and final project wrap-up.

Nov 7 - Nov 30 (Nov 30 eval)
  •    Final evaluation, completion of remaining tasks