Name | Time zone | Discord ID | Email ID |
---|---|---|---|
Mohit Vaish | IST | Mohitv#9920 | mohit_vaish@hotmail.com |
Communication channel: Discord+ Github
Project repo: https://github.com/hyperledger/bevel
...
Final Project Presentation:
- TBD
Milestones
Eval 1:
- Manual upgrade of non-chaincode parts the platform components (orderer, peer) of the network
- Manual upgrade of the application components (channel, chaincode) parts of the network
Eval 2:
- TBDOperation Guide on how to upgrade manually
Eval 3:
- TBDHelm and Ansible automation for upgrade of the components
Eval 4:
- TBDFinal Operation Guide and Video on how to upgrade using Hyperledger Bevel
Timeline
Dates | Tasks/Plan | Status |
---|---|---|
June 1 - June 14 | Mentee intro with the mentor. Introduction to the concepts of Bevel | Done |
June 15 - June 28 | Manual upgrade of non-chaincode parts of the network | Done |
June 29 - July 12 | Manual upgrade of chaincode parts of the network | Done |
July 13 - July 26 | Document the approach & manual upgrade tasks performed | Ongoing |
July 27 - Aug 9 | Automate the binary upgrade process for Orderer | Ongoing |
Aug 10 - Aug 23 | Automate the binary upgrade process for Peers and upgrade DB | |
Aug 24 - Sept 6 | Automate tasks for upgrade capabilities | |
Sept 7 - Sept 20 | Automate tasks to update EndPoints and Endorsement Policies | |
Sept 21 - Oct 4 | Automate tasks to update Lifecycle and ACLs | |
Oct 5 - Oct 18 | Test final automation | |
Oct 19 - Nov 1 | Update document | |
Nov 2 - Nov 12 |
...
Prepare final presentation and demo |
Methodology
The planned approach can be broken into following steps:
...