DatesTasks/Plan

Status

June 1 - June 14Mentee intro with the mentor. Introduction to the concepts of BevelDone
June 15 - June 28Manual upgrade of non-chaincode parts of the networkOngoing

June 29 - July 12

Manual upgrade of chaincode parts of the network
July 13 - July 26

July 27 - Aug 9

Aug 10 - Aug 23

Aug 24 - Sept 6

Sept 7 - Sept 20

Sept 21 - Oct 4

Oct 5 - Oct 18

Oct 19 - Nov 1

Nov 2 - Nov 12

Methodology

...

The planned approach can be broken into following steps:

  1. Perform a manual upgrade for all required steps and verify the results. Steps performed can be found here
  2. Automate the verified steps following the Bevel framework principles 
  3. Document the process and identify the manual tasks to be performed by the operator for this upgrade task