DateTasksDeliverables
June 22 – July 06 
  •  Review on interoperability 
  •  Initial System Design 
  •  Production level Infrastructure
  • Project Plan  
    •  Objective of projects 
    •  Use case scenario   
  • Metadata attributes design 
    •  Attribute name  
    •  Attribute explanation 
  • Documentation of architecture 
    •  Text based explanation 
    •  diagram  
July 06 – Aug 03 
  •  Implementation of ChainCodes  
  •  Implementation of relays 
  • Source Code  
    •  Gateway ChainCode 
    •  relay source code (on-chain)
    •  relay source code (offchain )
    •  Code will be published on production level infrastructure 
     
  • Code documentation 
    •  Text explanation of chain codes  
    •  Other details should be understandable by names of methods and variables (clean code) 
Aug 03 – Aug 17  
  •  Integration test 
  •  Evaluation (Security / Efficiency) 
  • A report on test and evaluation results 
  •  Determining bottlenecks 
  •  Report on failed and accepted tests and reasons 
  •  Report on efficiency and security test results and any applied improvements 

...