Priority

Policy 

(recommended actions)

P1

Very High

Added immediately to the current sprint taking priority over that work. It may very well require the effort of more than one team member, possibly including the whole team.
Alternatively notify security@pegasys.tech to invoke handling of the issues under the security playbookrefer to Security page if it is a security issue

P2

High

Added immediately to the current sprint and resolution starts as soon as logically possible. Ideally, should be resolved by the end of the sprint. Team decides who can best address the issue.

P3

Medium

Added as a priority for the next sprint, at the discretion of the product owner.

P4

Low

Documented. Discussed in the next sprint planning meeting at the discretion of the product owner.

Candidate for a Good First Issue for the community.

P5

Very Low

Documented in list of known issues. Revisited only if severity or probability increases or at the discretion of the product owner.