Week

Deliverables

Status

June 1 - June 7

  • Read Documentation for HL Besu.
  • Read Documentation for Operator framework.
  • Get accustomed to the Go programming language.
  • Environment Setup.
  • Discuss the high-level design of the project with mentors.
  • Document the process
  •   

June 7 - June 21

  • Prepared, automated installation of an application using operator
  • Document the process
  • Get feedback from the mentor
  •   

June 21

  • Submission for 1st Quarter Evaluation

June 21 - July 7

  • Add support for seamless patch and minor version upgrades.
  • Document the process
  • Get feedback from the mentor
  •   

July 14

  • Submission for 2nd Quarter Evaluation

July 7 - July 14

  • Add support for app/storage lifecycle, backup, failure, recovery
  • Document the process
  • Get feedback from the mentor
  •   

July 14 - July 21

  • Add monitoring capabilities to the operator.
  • Document the process
  • Get feedback from the mentor
  •   

July 31

  • Submission for 3rd Quarter Evaluation

July 21 - August 1

  • Set up instructions for the user to deploy the operator in various scenarios
  • Document the process
  • Get feedback from the mentor
  •   

August 1 - August 21

  • Code Reformatting
  • Error Handling
  • Clean up the documentation
  • Thorough Testing
  •   

August 21

Final Evaluations


...