Current Release Process

The latest Hyperledger Fabric release process can be found in the Release Process google document.

See FAB-4379 for a template JIRA

Proposals

Weekly release cadence - CBF

  • begin merge moratorium on Weds am at 8 am ET
  • ensure Daily and Weekly tests are run, force repeated CR CI passes of each repository
  • if significant issues found, defer release for following week (no sense killing ourselves)
  • if no significant issues found, proceed with release
    1. create Task for weekly release, cloned from this JIRA Task
    2. assign a release manager to the execution (should not try to coordinate steps, this is where errors of mis-communication occur)
    3. begin the release process at 8am Thursdays
    4. on successful testing of download/images/docs review and e2e testing, spam announce email
  • lift merge moratorium