Week | Deliverables | Status |
June 1 - June 7 | - Read Documentation for HL Besu.
- Read Documentation for Operator framework.
- Get accustomed to the Go programming language.
- Environment Setup.
- Discuss the high-level design of the project with mentors.
- Document the process
| |
June 7 - June 21 | - Prepared, automated installation of an application using operator
- Document the process
- Get feedback from the mentor
| |
June 21 | - Submission for 1st Quarter Evaluation
|
|
June 21 - July 7 | - Add support for seamless patch and minor version upgrades.
- Document the process
- Get feedback from the mentor
| |
July 14 | - Submission for 2nd Quarter Evaluation
|
|
July 7 - July 14 | - Add support for app/storage lifecycle, backup, failure, recovery
- Document the process
- Get feedback from the mentor
| |
July 14 - July 21 | - Add monitoring capabilities to the operator.
- Document the process
- Get feedback from the mentor
| |
July 31 | - Submission for 3rd Quarter Evaluation
|
|
July 21 - August 1 | - Set up instructions for the user to deploy the operator in various scenarios
- Document the process
- Get feedback from the mentor
| |
August 1 - August 21 | - Code Reformatting
- Error Handling
- Clean up the documentation
- Thorough Testing
| |
August 21 | Final Evaluations |
|