Week | Task/Plan | Status |
---|---|---|
May 25 - May 29 | Mentee intro with the mentor. My case I am already communicating with the mentor(Sean) | Done |
June 1 - June 14 | Implement basic functionality of VScode extension. Syntax highlighting of Solidity language. | Done |
June 15 - June 28 | Rust server for receiving the incoming requests from VScode clients. | Done |
June 29 - July 5 | Buffer period to complete the remaining work and co-op with difficulties during implementation. | Done |
July 6 - July 12 | Complete tests and documentation of the Rust server impl. Eval on July 10: Provide reports for first quarter to the program organisers. | Done Ready for eval |
July 13 - July 26 | Work on the code compilation of Solidity. Prepare the backend to process incoming code. | Done |
July 27 - August 9 | Work on diagnostics, fixing Range issues and fixing minor bugs. | Done |
August 10 - August 16 | Buffer period to complete the remaining work and co-op with difficulties during implementation. | Done |
August 17 - August 23 | Complete tests and documentation of the diagnostics implementation. Eval on August 21: Provide reports for the second quarter to the program organisers. | Done Ready for eval |
August 24 - Sept 6 | Work on the symbol definition feature. List out all possible grammar definitions and start implementing. | |
Sept 7 - Sept 20 | Follow up on the work. | |
Sept 21 - 27 | Buffer period to complete the remaining work and co-op with difficulties during implementation. If everything is under schedule, start implementing code formatting feature. | |
Sept 28 - Oct 4 | Complete tests and documentation of the implementation. Eval on Oct 2: Provide reports for third quarter to the program organisers. | |
Oct 5 - Oct 18 | Work on the code formatting feature. | |
Oct 19 - Nov 1 | Publish the first version on the VScode extension store. *Work on additional features. | |
Nov 2 - Nov 8 | Buffer period to complete the remaining work and co-op with difficulties during implementation. | |
Nov 9 - Nov 13 | Complete tests and documentation of the remaining implementation. Eval on Nov 13: Provide final reports for fourth quarter to the program organisers. |
...