The tentative timeline is as follows:

Week

Deliverables

Week 1 - Week 3 


  •  Introduction and kick-start project plan
  •  Familiarising with latest version updates in Fabric
  •  Discussion over architecture
  •  Listing requirements and features of the platform
  •  Create a simple network mimicking the MVP
  •  Writing chaincodes to invoke actions

Week 4 - Week 6

  •  Working on additional features for user and council
  •  Setup unit tests and CI
  •  Writing testing requirements for the project
Week
6
7 - Week 9
  •  Incorporate the network with Web UI
Week 10 - Week 12
  •  Developing a mobile application for the platform
Week 13 - Week 15
  •  Documentation
Week 16 - Week 18
  •  Documentation
Week 19 - Week 21
  •  Documentation
Week 22 - Week 23
  •  Completing documentation
  •  Wrapping up with any pending work/feature

Newly suggested features will also be incorporated during the course of the project.

...